See my interview with an Atkins engineer here:
In Summary he told me the following information:
- 1 metre per shift of tunnelling is made in each tunnel entrance
- North bound (from the south) tunnel now 30 metres in
- South bound (from the south) about 15 metres
- Excavation by excavator trucks NOT a huge drill - just not economic.
- Cutting before tunnel will be 20 metres deep!
- A footbridge to Anne's house will be made
- Opening on target for August 2011
Please post your views and any news of the tunnel or correct any errors